Excess treated waste water from STP in an apartment complex is 100 KLD.Total water requirement is 771 KLD -Kindly provide suggestions to solve the issue

Dear Sir/Madam,

We have a residential project with multistorey apartments & villas with premium quality facilities. Entire project will be done in two phases. we are at initial phase of the project.

Issue: DISPOSAL OF EXCESS WASTE WATER FROM STP - QUANTITY - 100 KLD

Design Calculation as follows: (PFA)

Total water requirement (Residential & Amenities) - 771 KLD

Waste Generation (80%) - 618.32 KLD

Treated Waste Water Generation from 03 No.of proposed STP's - 525.57 KLD

Treated Waste Water Reuse Potential (For Flushing/Landsacepe & Amenities) - 452.31 KLD

Excess Treated Waste Water - 73.26 KLD (In summer) & 248.67 (In Monsoon)

Request you to kindly provide your opinions/suggestions to resolve this issue.